The environmental aspect of Port 2000 has been integrated, from the beginning,
in the project. The very phasing of the construction site has been chosen to
reduce the impact on the estuary to the minimum. In addition,
more than EUR 46 million have been allocated to it (which is a première for port works),
half of which for the restoration of the mudflats, a complex project but an essential
one for life in the Seine Estuary.
The very first site carried out for Port 2000 has been an environmental work.
The dune bird sanctuary was indeed completed in February 2002, whereas port works had just begun…
One of the technical difficulties in Port 2000 will have been the completion of the two types of
work at the same time, all having to be studied, selected and implemented to limit the impact of
the port works on the estuary environment and on sedimentology as much as possible (accompanying
dredging operations, phasing of the breakwater works, design of the structures with maximum re-use
of the materials of the site itself…).
This first cooperation trial between developers and environmental actors in a
port construction site located in an estuary led to a close work with the different
bodies concerned (DIREN -Regional Division of the Environment-,
Maison de l’Estuaire –Estuary House, environmental associations…).
Being the result of the public debate, the cooperation initiated is due to
continue and is today a major asset for the Seine estuary.
A – THE RESTORATION OF THE MUDFLATS, A MAJOR ELEMENT IN THE ENVIRONMENTAL PART OF PORT 2000
Begun in the summer of 2003 after simulations on models (carried out by SOGREAH with DIREN as
the contracting party and under supervision of a committee of experts), the works for the restoration of
the mudflats is due to be completed in late 2005. Several stages have indeed been thought necessary
in order to give time to nature to take its course again.
The first step consisted in creating the substructure of the groin, in the summer of 2003, in the northern
part of the estuary at right angles with the radar tower in Honfleur. The changes noted in situ
(reduction in bottom depth and beginning of a mudflat) confirmed the studies, which permitted to
launch the second phase of work. From September to December 2004, the groin was raised on almost
all the length (500 metres) and the lower Northern breakwater on a length of 2,000 metres
(downstream the Normandy bridge, between the opening and the groin).
The third and last stage of this programme aims at improving the water circulation
and creating additional mudflats upstream the Normandy Bridge to protect fish nurseries.
Begun in late 2004, it includes the digging of an environmental channel and the creation of an
opening at the upstream outlet of the channel while raising the present opening.
The invitations to tender for this last stage were launched during the summer of 2003,
and the tenders were addressed for this contract of design/completion in December of the same year.
In early 2004, a selection committee made up of PAH, PAR, DIREN, the ‘Maison de l’Estuaire’ and the Le Havre Chamber of Commerce
and industry (CCIH) met to study the tenders. The SODRANORD Company, a subsidiary of the Dutch group VAN OORT,
expert in studies and completion of dredging works, was selected, as its technical solution was the most
respectful for the environment especially because putting dredged materials ashore is carried out by
pipes and the placing and removing of the pipes takes place before the nesting period and after the young
birds have left the nest.
SODRANORD made the most of the summer of 2004 to complete the studies of the project
and the specifications, on the basis of the guidelines provided by the Port Autonome du Havre. As prime contractor
and work contractor for this work site, SODRANORD began the works end of 2004 by the development of a deposit area,
north of the Estuary Highway. Connected to the dredger by 2.5 km of pipes (including a shore part and a floating one),
this deposit area receives the materials collected by the stationary suction dredger “AEGYR”.
After settling of the sediments dredged from the docks,
the water received in the deposit area is pumped towards the Seine estuary,
thus re-supplying the existing ‘filandres’ (local name for the drainage channels
of the slikke) to guarantee their long-term existence in a better way.
Prior to the dredging of the environmental channel, additional protection of the northern
access piles of the Normandy bridge was carried out. This meant digging an underwater excavation, between February
and mid-March 2005, at the foot of the piles and, afterwards, a pontoon brought rock-fills there, to get a protection
against erosion. Dredging works have then begun : they involve 1.8 million cubic metres of sediments on-site
(mixed materials made up of sand and mud), corresponding to the dredging of a
channel 100 metres wide (from north to south) and on a length of 2,800 metres (from west to east).
Positioned owing to its GPS, the dredger is maintained by a rear pile and two anchors on each side.
It is said that it ‘moves like a butterfly’, because it carries out circle movements with several goes.
It is equipped with a cutter (or cutterhead) with a suction head connected to a pump whose output is 4m/s
and the pressure 6 bars : 900 m3 of sediments are thus pumped in every hour.
The last stage of this work site, scheduled for the autumn of 2005, involves
the creation of a new opening at the upstream outlet of the environmental channel and raising
of the downstream opening in order to facilitate the free flow. All the works are due to be
completed by the 3rd quarter of 2005.
B – CREATION OF A REST PLACE FOR BIRDS IN THE SEINE ESTUARY
After 165 days of work and some 600 trips with nautical craft, the rest place for birds
located in the southern part of the estuary (in front of Villerville) has just been completed. Constructed by
“ATLANTIQUE DRAGAGE” – a subsidiary of the Dutch group BOSKALIS – on the basis of the studies and survey on model
previously carried out, this unique site is 320 m long and 200 m wide.
Its main characteristics (shape, level of the grounds) have been decided first of all
in very close cooperation with the Upper and Lower-Normandy “DIREN” and the ‘GON’ (Groupe Ornithologique
Normand : Normandy Ornithological Society). Designed to receive sea birds and diversify the reception and rest
places for the various species, this 5-hectare sanctuary which is unbroken at low tide, is divided
into 3 separate emerging islets at high tide, with a total surface of 1.5 hectare.
Being a true technical achievement owing to the complex shape of the sanctuary and
its situation in the estuary, the works began in early October 2004 and were completed in mid-April 2005.
On-site, 4 craft (1 self-propelling barge, 1 barge, 1 dredger and 1 discharging barge and 5 shore machines
(2 bulls, 2 shovels and 1 loader) have worked simultaneously to carry out the deposit of
57 000 tonnes of rock-fills from the Cotentin and 610 000 tonnes of sand and gravel materials
coming from the dredging operations performed in the future channel of Port 2000.
The personnel of the Maison de l’estuaire excepted, as they will control the coming
of birds and the possible settling of fauna and flora species, any presence of human beings is forbidden,
in compliance with the decree of the Nature Reserve in order to preserve the tranquillity of the place.
C – ADDITIONAL DEVELOPMENT FOR THE DUNE SANCTUARY FOR BIRDS
As the first environmental measure to be implemented, the works for the creation of the dune sanctuary
for birds were completed as early as February 2002. Since then, a follow-up survey of how it works and how often
it is used is carried out in connection with the DIREN and the ‘Maison de l’Estuaire’, the manager of the Nature
Reserve of the Seine Estuary. The observations made are very encouraging and have made it possible to define a
few additional measures to improve the functioning even further, as regards especially the management of the water
levels of the dune sanctuary.
In order to improve the reception capacity of the dune sanctuary, additional development was made
in mid-July and August 2003 in the North-Eastern part of the sanctuary. This arrangement aims at receiving
the avocets for nesting. The reshaping works included the digging of a network of always submerged ditches
around five islets with gentle slopes. This system is kept apart from the rest of the sanctuary by earthworks,
a duct equipped with a non return valve makes it possible to manage precisely water levels (in and out)
and to remain independent of the water management of the rest of the sanctuary.
This management requires setting up a structure of water level management for the sanctuary.
Two places to set up the structure were studied by an external project management within
the scope of the preliminary design study (to have a look at both sites, click on the photograph below).
After study of all advantages and drawbacks of each of the two sites, the ‘A’ site was selected by the
steering committee (DIREN, MDE, PAH) as it favourably meets the requirements of the structure and
the environmental conditions. The aim is to be able to set water levels which can vary according to the period.
The water analysis and the feasibility study have made it possible to define
a mobile structure (see 3-D diagram) whose main characteristics are as follows :
- a flat gate, made up of two mobile parts, independent of each other and making it
possible to get fixed water levels, in tidal rise or not.
- a flowing rise to maintain the water level (during spring tides) at the minimum level of
(+ 8.50m according to Le Havre Marine Chart Data).
Of course, with a high tidal coefficient and a water level higher than
(+ 8.50 m according to Le Havre Marine Chart Data), all the zone will be flooded. The table
below sums up the functioning of the structure according to the various situations considered : (see diagram)
The project design stage was presented to the steering committee by the service
company BRL/ISM (prime contractor) on April 8th, 2004. The invitation to tender was launched in the fall
of 2004. The works were carried out from December 2004 to mid-May 2005.
They included the construction forward of a sea breakwater of about 133m with a
flowing rise of 50m, a civil engineering structure in prefabricated elements and a gate structure.
All environmental works – whose completion is scheduled by end of 2005 – go together
with a significant scientific follow-up which makes it possible to assess the efficiency of the developments made.
A specific follow-up of fishing resources has been carried out for several years and is going to continue once
the works are completed.